(AI) Air India 816 Flight Details
Delayed by 3h 5m | Scheduled
Departure
BOM
Mumbai Chhatrapati Shivaji International Airport, IN
Flight Gate Times
04-May-2025
Scheduled
21:00
IST
Estimated
00:05
IST
Total Departure Delay: 3 h 5 mins
Flight Runway Times
04-May-2025
Scheduled
--
Actual
--
Runway Delay: -
Terminal
2
Gate
-
Craft Type
Boeing 777-300ER
77W
Flight Time
Scheduled
2h 15m
Arrival
DEL
Delhi Indira Gandhi International Airport, IN
Flight Gate Times
04-May-2025
Scheduled
23:15
IST
Actual
--
Total Arrival Delay: -
Flight Runway Times
04-May-2025
Scheduled
--
Estimated
02:10
IST
Runway Delay: -
Terminal
T3
Gate
-
Baggage Claim
8
Tail Number
VT-ALK
Flight Time
-
Flight Notes
Also marketed as (LX) Swiss 9855
Event Timeline
Date
Event
Data Updated
4 May
02:18
07:48
07:48
Time Adjustment
Estimated Gate Departure changed from May-04-2025 9:45 PM to May-05-2025 12:05 AM
4 May
02:18
07:48
07:48
Time Adjustment
Estimated Runway Arrival changed from May-04-2025 11:50 PM to May-05-2025 2:10 AM
4 May
00:05
05:35
05:35
Gate Adjustment
Arrival Terminal changed from 3 to T3
Baggage changed to 8
3 May
14:27
19:57
19:57
Time Adjustment
Estimated Gate Departure changed to May-04-2025 9:45 PM
3 May
13:16
18:46
18:46
Equipment Adjustment
Tail Number changed from VT-JRI to VT-ALK
Actual Equipment changed from 359 to 77W
3 May
13:16
18:46
18:46
Time Adjustment
Estimated Runway Arrival changed to May-04-2025 11:50 PM
3 May
06:03
11:33
11:33
Equipment Adjustment
Tail Number changed from VT-JRE to VT-JRI
3 May
05:16
10:46
10:46
Equipment Adjustment
Tail Number changed from VT-JRI to VT-JRE
2 May
07:47
13:17
13:17
Equipment Adjustment
Tail Number changed to VT-JRI
Actual Equipment changed to 359
1 May
18:11
23:41
23:41
Record Created
1 May
18:11
23:41
23:41
Time Adjustment
Scheduled Gate Departure changed to May-04-2025 9:00 PM
Scheduled Gate Arrival changed to May-04-2025 11:15 PM
Departure Terminal changed to 2
Arrival Terminal changed to 3
Scheduled Equipment changed to 359